Hey Contractors, How To Fill Out Aia Pay Apps - Part 1

 
[ Contact the Author] [ Send to a Friend] [ Article Publisher] [Make PDF] [ Print] [ Bookmark & Share]
 
Read our Terms of Service before reprinting this article. The submitter specified above has claimed the rights to this article.
Ron Roberts

If we grabbed the first 10 small subcontractors you crossed paths with and tested them on filling out AIA pay applications, 7 or more would probably fail the test. At least, that's about the error rate I've seen while reviewing pay applications.

AIA pay applications are frustratingly difficult to fill out. To fill one out correctly, you must ignore change orders that have been approved, but not processed. You must ignore receivables still outstanding from previous applications.

Basically, you have to divorce yourself from reality.

Pay apps are an important component of cash management. When you screw up your pay app, three things might happen, none of which put you in good standing with your general contractor, and two of which damage your cash position:

1. Your project manager cuts your request to a value he can understand. You receive a partial payment.

2. Your project manager informs you that you if you don’t get a corrected application in by the deadline, you will have to wait another 30 days for payment. You may not receive any payment.

3. Your project manager makes the corrections himself and may hold it against you in the future when you need a favor or are looking for work. Like the rest of us, project managers like working with people who don't create headaches.

You really have no choice other than learning how to fill out the AIA form correctly.

I am going to show you how to fill one out correctly. In Part 1, we attack the first page (AIA form G702) and in Part 2 we will work on the second page (AIA form G703).

Before we get started, grab a copy of the form. If you don’t have access to one, drop me an email and I’ll send you the form.

Line 1, Original Contract Sum.

The price the GC agreed to pay you for the scope of work you agreed to perform. This includes all accepted alternates.

Pull out your contract. Look at it. This number should NEVER change from your first pay application to your last.

Assume your contract was for $900,000.

Line 2, Net Change by Change Orders.

Here it is. The line that creates much frustration.

Add up all of the change orders that have been priced and FORMALLY approved by the GC. If the project manager is sitting on your change order paper work, call him at least a week before your pay application is due and URGE HIM to complete the paper work. Being the squeaky wheel is often your only recourse.

Assume the GC has processed and signed $100,000 in change orders.

Line 3, Contract Sum to Date

This should be easy. Add the numbers on lines 1 and 2. This is your OFFICIAL contract sum at the date of this pay application.

Your contract sum to date is $1,000,000 ($900,000 plus $100,000)

Line 4, Total Completed and Stored to Date

This value comes from the left side of column G on page 2. The box is the fourth from the left, bottom row.

For now assume that you have completed $500,000 of work and have stored $50,000 of materials in approved storage sites.

Your line 4 total would be $550,000.

Line 5, Retainage (three lines).

Your contract should set the terms of retention. If it doesn’t, demand that no retention be withheld! If the GC failed to put retention in your contract, do not allow him to use it.

On a side note, if you happen to be providing a performance bond, retention is not justified. The bond serves the same purpose as the retention.

Line 5a, _% of Completed Work.

In the blank next to the "a.", write down the current retention percentage. Typically, it is 10%. Your contract may allow you to reduce the retention to 5% near substantial completion.

In the blank next to the dollar sign, you need to write down the dollar value of retention that applies to your completed work. To arrive at that number, turn to page 2 and add together the values from the bottoms of columns D and E. Multiple by 0.1 if the retention is 10% or by 0.05 if the retention is 5%.

Assuming 10% retention and $500,000 of completed work, write down $50,000.

Line 5b, _% of Stored Materials.

Repeat the process used for Line 5a except use the value from the bottom of column F on page 2 .

Usually, the retention for completed work and stored materials is the same. Write down whichever rate is contracted next to the "b.". In the blank next to the dollar sign, write down the retention for your stored materials.

Assuming 10% retention and $50,000 of completed work, write down $5,000.

Line 5 Total Retainage.

Add together the totals from lines 5a and 5b. This value should match your total of column I on page 2.

For our example, the figure would be $55,000.

Line 6 Total Earned Less Retainage

What you’ve earned, as far as approved change orders are concerned, is on line 4. What the client is allowed to retain is on line 5. Subtract the Total Retainage ($55,000) from your earned revenue ($550,000) and enter the difference ($495,000) on Line 6.

Line 7 Less Previous Certificates for Payment

The pay application has now entered the twilight zone. Confusion is caused by generals and owners who take so long to pay that you are submitting your next pay application before the previous one gets paid.

Natural instinct is to write down payments received to date on line 7 and ignore pay requests being processed. Don’t do that. Trust the paper trail. This pay application doesn’t care whether you’ve been paid. It only cares whether you’ve earned additional payment.

Go back to your immediately preceding pay application and write down the value from Line 6 Total Earned Less Retainage on that application. For the sake of our example, assume you had submitted to date on $400,000.

Line 8 Current Payment Due

Take your Line 7 value ($400,000) and subtract it from your line 6 value ($495,000). Write down the difference on Line 8 $95,000).

This represents the value you should be paid for worked earned during this pay period AND any change in retainage during the pay period.

Line 9 Balance to Finish Including Retainage

Take the contract sum to date from Line 3 ($1,000,000) and subtract the Total Earned Less Retainage from Line 6 ($495,000). This tells the General Contractor that he is contracted to pay you an additional $505,000 AFTER paying this application.

This is another confusing line because it acts as if all change orders have been formally processed and that all previous pay applications have been paid in full. What a dream world the AIA
lives in.

Frequently, clients and GCs only pay part of your application. The AIA form never reflects partial payment of an application. It wasn’t designed to. Keep track of what’s been paid vs. what’s been earned and invoiced (applied for).

The table at the bottom of page one is fairly straight forward. You will need to separate the change orders that add money to your contract from those that subtract money from your contract. The Net Changes by Change Order should be exactly equal to the value you entered on line 2.

In summary, following the instructions and you have a shot at getting paid everything you're owed.

Important NoticeDISCLAIMER: All information, content, and data in this article are sole opinions and/or findings of the individual user or organization that registered and submitted this article at Isnare.com without any fee. The article is strictly for educational or entertainment purposes only and should not be used in any way, implemented or applied without consultation from a professional. We at Isnare.com do not, in anyway, contribute or include our own findings, facts and opinions in any articles presented in this site. Publishing this article does not constitute Isnare.com's support or sponsorship for this article. Isnare.com is an article publishing service. Please read our Terms of Service for more information.

Ron Roberts, The Contractor's Business Coach, teaches contractors how to turn their businesses into a profit spewing machines. To receive Ron's FREE Contractor Best Practices Newsletter visit http://www.FilthyRichContractor.com.
Article Tags: line [See Dictionary], pay [See Dictionary], retention [See Dictionary]
Got a question about this article? Ask the community!
Article published on August 09, 2007 at Isnare.com
 
Rate [Ratings: 0 / 5] [Votes: 1]

Hey Contractors - Here's How To Structure Your Company For Success And Growth
Submitted by: Ron Roberts

What does structuring your business mean and why is it important that you structure it right Structuring your business means that you’ve identified the tasks and processes that must be carried out properly in order to keep your business running...

Hey Contractors, These Staffing Systems Get The Right People On The Bus And In The Right Seats
Submitted by: Ron Roberts

In another article titled How Contractors Get Rich, I introduced you to the six systems that control the fate of your construction business...

Hey Contractors: With Decision Making - Focus On The Process, Not The Outcome
Submitted by: Ron Roberts

Developing people, helping them grow as contributors, and helping them feel pride in their work produces great benefits to your company...

Hey Contractors, Make Your Crews Fix Their Own Interpersonal Conflicts
Submitted by: Ron Roberts

You’ve got a headache on your hands What should you do...

Hey Contractors, Here's How To Survive Close-Out
Submitted by: Ron Roberts

During the lead up to substantial completion, problems start popping up like crabgrass You can’t stop them...

Hey Contractors, Push Leadership Into Your Crews
Submitted by: Ron Roberts

Are you trying to build a business or are you trying to work yourself to death The question constantly runs through my mind when chatting with contractors about their situation, their dreams and goals, and their frustrations...

Hey Contractors, Here's How To Know Your Project Is Headed For Disaster
Submitted by: Ron Roberts

Don’t you just hate it when good jobs turn bad You get the job at a good price...

Hey Contractors, Here's How To Staff A Championship Team
Submitted by: Ron Roberts

Do you struggle finding good workers Your staffing strategy may be the problem...

Hey Contractors, Make Your Advertisements Stand Out
Submitted by: Ron Roberts

Go grab your Yellow Pages Now open it up to the page where your services are advertised...

Hey Contractors, You Lose Money When You Lose Their Trust
Submitted by: Ron Roberts

Trust is a precious commodity Trust creates bonds that last forever...

Hey Contractors, Contact Management For Low Tech People
Submitted by: Ron Roberts

Have you ever taken the time to sit down with an old timer and ask him the key to his success Amazing what you can learn if you are willing to listen to retired businessmen...

Hey Contractors, How To Keep Quality Control Simple
Submitted by: Ron Roberts

When asked why you should be chosen over a competitor, do you respond with "because we do things right"...

Movers: 7 Keys To Finding The Right Moving Company
Submitted by: Timothy Clendaniel

________________________________________ Quick Summary ________________________________________ 1Get referrals from local real estate agents and friends who have moved recently...

Never Say No to Cape Town Property
Submitted by: Elizabeth McLachlan

Cape Town is well known for its spectacular views of mountains and sea, making it hard to find a property in this popular city that does not have a room with a view of either Table Mountain, sprawling Atlantic Ocean or rolling wine lands...

9 Questions to Ask When Choosing a Property Portal
Submitted by: Elizabeth McLachlan

A good property portal is an extremely useful marketing tool for estate agents or those opting to sell privately...

How Does Dubai’s Debt Impact Calgary Real Estate?
Submitted by: J. Samson

Here we go again Better hang on to what you’ve got because another financial correction of our not quite yet recovered economy is coming...

What Are My Building Costs Per Square Meter?
Submitted by: John Wrighty

A very common question asked by a new home buyer is "What will the building costs be per square metre...

Moving? The 5 Biggest Moving Myths
Submitted by: Timothy Clendaniel

One of the great things about moving is that so many other people have been through it before you In fact, the U...

Selling Your Home in a Buyer's Market
Submitted by: Stephen A Daniels

The news headlines today are full of some depressing news about the housing market The market is showing signs of improving, so obviously some people are successfully selling their homes...

Buying and Restoring Historic Homes
Submitted by: Stephen A Daniels

What Defines a “Historic Home” It is interesting to note that the National Registry of Historic Places requires a home to be at least 50 years old and look much the same as it did when built...

How To Sell A House With Pets
Submitted by: Lori Lovely

According to the American Pet Products Manufacturers Association 2007-2008 National Pet Owners Survey, 39 percent of U...

Top Benefits From a Real Estate Investment Guide
Submitted by: Seomul Evans

What data can you get from a good real estate investing book There are a numeral of online sites, which can bring out you knowledge and points on how to begin arrive at your real estate investments properly...

Tips For Smart Real Estate Investments
Submitted by: Seomul Evans

Numerous people are questioning what real estate investing is all about Even if you are a small real estate investor, you will still have high earning potential...

Tips to Stopping a Foreclosure?
Submitted by: Seomul Evans

People around the world are acquiring more service oriented and the service sector is experiencing a period of high demand...

How to Select a Top Real Estate Agent?
Submitted by: Seomul Evans

Buying a new home is a big investment and you want things to go as smoothly as possible Numerous people choose to do affairs on their own however this can lead to many another problems down the road...

Oak Park and the Housing Downturn
Submitted by: Mike Landis

While the national real estate market experienced a downturn over the previous two years, the property market in Oak Park has held up reliably well...

Tips For Selling Your Home in a Tough Real Estate Market
Submitted by: Michael E. Taylor

There is certainly no dearth of home sellers in the market today given the worrisome economic situation but the same cannot be said about buyers...

Isnare.com Footer Divider

© 2004-2009. Isnare Free Articles - An Isnare Online Technologies Free Articles Project. All Rights Reserved.   Privacy Policy